CPF (Campus Planning and Facilities) will be performing high voltage power maintenance as follows:
•North Campus - shut down to perform high voltage power maintenance
•South Campus - shut to pull a new high voltage feed to SE08 and fixing an issue in SE06
The IT Services Data Centre is located in SE12 and is expected to be fully operational using generator and UPS power during this CPF maintenance:
•All network connectivity will be unavailable from the impacted buildings
•All systems should be accessible from off campus or from non-impacted buildings.
•On campus classes for this weekend have been shifted from affected buildings to buildings that are not affected (i.e. SW09)
Please note that buildings SE16, SE40, SE41, SE42, SE50, SW07 (TTSH), SW09 and SW10-SW16 (Residences) will not be affected on any of the days.
Summary of power outages by building:
Saturday August 2, 2025 8:00am-9:00pm
NE02, NE04, NE06, NE07, NE08, NE09, NE10, NE12, NE16, NE18, NE20, NE22, NE23, NE24, NE25, NE28,
NW01, NW03, NW04, NW05, NW06,
SE01, SE02, SE04, SE06, SE08, SE09, SE10, SE12, SE14, SE30,
SW01, SW02, SW03, SW05.
Sunday August 3, 2025 8:00am-9:00pm
NE01, NE03, NE12,
NW04,
SE01, SE02, SE04, SE06, SE08, SE09, SE10, SE12, SE14, SE30,
SW01, SW02, SW03, SW05.
Monday August 4, 2025 8:00am-9:00pm
NE16, NE18, NE20, NE22, NE24, NE28,
NW01, NW03, NW05, NW06,
SE01, SE02, SE04, SE06, SE08, SE09, SE10, SE12, SE14, SE30,
SW01, SW02, SW03, SW05.